Corinna Gries, 09/12/2013 01:01 PM

1 1 Corinna Gries
h1. Project Team Meetings
2
3 7 Corinna Gries
h2. next meeting: 9/17/2013
4
5
6 6 Corinna Gries
h2. 8/27/2013
7
8
Matt, Scott, Syd, Sam, Corinna
9
10
reports:
11
Matt is still trying to hire a programmer
12
Corinna announced project at LTER IM meeting and got several responses regarding datasets available. Specifically GCE, LUQ, and VCR
13
Syd has started R programming for some community change indeces
14
15
workshop planning:
16
start document for goals, participants and agenda
17
18
action items:
19
Corinna start document for workshop planning
20
Syd and Sam communicate about R routines for data manipulation
21
Syd and Scot get names of datasets from SEV and KNZ to Corinna
22
Corinna and Sam work with Kristin and Adam to get EML for those datasets
23
24
25 3 Corinna Gries
h2. 6/13/2013
26 1 Corinna Gries
27 6 Corinna Gries
Matt, Scott, Syd, Sam, Corinna
28 5 Corinna Gries
29 2 Corinna Gries
Agenda
30 4 Corinna Gries
Action items from last meeting
31 2 Corinna Gries
Scott - report from the Science Council meeting re. datasets
32
Matt - intro to project management system and start of tracking Community Change indices
33
Corinna - start list of participants for first workshop at NCEAS
34 4 Corinna Gries
35
Notes
36 5 Corinna Gries
Scott announced the project at the LTER Science Council meeting
37
Important to remember is that we have support to clean data and document them in EML. We are not expecting the information managers at other sites to add this to their tasks. We can take datasets that have at least 10 data points at even time intervals.
38
39
Action items:
40
Matt: add functionality to this project management system to track datasets from a general idea of its existence to actually being in the NIS/DataONE
41
Corinna: start adding Community Change indices from the proposal to redmine. 
42 2 Corinna Gries
43 1 Corinna Gries
h2. 5/2/2013
44
45
Matt, Syd, Corinna
46
47
Today we filled Syd in a bit on her role in the project and talked some more about the first workshop in spring 2014.
48
49
Action items:
50
Corinna - doodle for the community workshop in February/March and set date
51
Syd - download and explore Kepler
52
Scott and Syd - start list of community change metrics that we want to encode
53
Matt - hire programmer
54
55
Next project team meeting: 6/13/2013 1 pm MDT