Project

General

Profile

Activity

From 11/23/2008 to 12/22/2008

12/18/2008

10:18 AM Bug #3650: move MET station to McLaughlin and begin work on Engineering view
For the Campbell order, MSI sends an update: "estimated time of arrival for your order is 12/29/08". Derik Barseghian

12/16/2008

02:11 PM Bug #3650: move MET station to McLaughlin and begin work on Engineering view
Received Campbell Sales Order Acknowledgment. Est Ship Date: 01-06-08. Derik Barseghian

11/24/2008

03:39 PM Bug #3650: move MET station to McLaughlin and begin work on Engineering view
Submitted order in form of 2 MSI preliminary requisition forms to Mark S. and MSI Purchasing.
According to the form,...
Derik Barseghian
 

Also available in: Atom