12/23/2008

12:37 PM Bug #3650: move MET station to McLaughlin and begin work on Engineering view
Apogee sends ETA for their order: 1/22/2009 Derik Barseghian

12/18/2008

10:18 AM Bug #3650: move MET station to McLaughlin and begin work on Engineering view
For the Campbell order, MSI sends an update: "estimated time of arrival for your order is 12/29/08". Derik Barseghian

12/16/2008

02:11 PM Bug #3650: move MET station to McLaughlin and begin work on Engineering view
Received Campbell Sales Order Acknowledgment. Est Ship Date: 01-06-08. Derik Barseghian
 