Activity
From 12/17/2008 to 01/15/2009
01/15/2009
- 11:35 AM Bug #3650: move MET station to McLaughlin and begin work on Engineering view
- Campbell order has arrived. Apogee order should arrive by Wed or Thurs next week.
01/09/2009
- 05:50 PM Bug #3650: move MET station to McLaughlin and begin work on Engineering view
- UPS sends update: Campbell order scheduled for delivery 12 Jan. It's in Salt Lake City today. 43 lbs.
01/07/2009
- 11:41 AM Bug #3561: add sst quality mask
- This is implemented as of r214.
12/23/2008
- 12:37 PM Bug #3650: move MET station to McLaughlin and begin work on Engineering view
- Apogee sends ETA for their order: 1/22/2009
12/18/2008
- 10:18 AM Bug #3650: move MET station to McLaughlin and begin work on Engineering view
- For the Campbell order, MSI sends an update: "estimated time of arrival for your order is 12/29/08".
Also available in: Atom