02/24/2009

01:20 PM Bug #3650: move MET station to McLaughlin and begin work on Engineering view
It should be noted that plot 28, a fenced plot, has not been instrumented. As both light bars were munched on, we wer... Derik Barseghian
01:08 PM Bug #3650: move MET station to McLaughlin and begin work on Engineering view
Station has been deployed to McLaughlin.
There are many loose ends and improvements I would like (not listed in this...
Derik Barseghian

02/12/2009

06:07 PM Bug #3650: move MET station to McLaughlin and begin work on Engineering view
Flying to PDX morn of Feb 15. Rented a 10' Budget truck to drive south, a bit obnoxious, but the cheapest soln for a ... Derik Barseghian

02/02/2009

04:27 PM Bug #3650: move MET station to McLaughlin and begin work on Engineering view
- buy fish tape
- determine pvc lengths and layout
map of site:
http://www.google.com/maps/ms?ie=UTF8&t=h&msa=0&msid...
Derik Barseghian
12:16 PM Bug #3650: move MET station to McLaughlin and begin work on Engineering view
Apogee order arrived some time ago.
Feb 16 is a holiday, Baskett office is closed. I can still disassemble the stati...
Derik Barseghian
 